Construction of a new centrifuge wastewater treatment plant and upgrade of the existing centrifuge wastewater treatment plant in Sooke, BC on Vancouver Island.
Scope Items
Assume responsibility of owner-supplied sequencing batch reactor (SBR) 3 equipment, sludge thickener, polymer system, and sludge feed pump via Novation Agreement.
Assume responsibility of owner-supplied sludge thickener discharge pump via free issue.
Construction of a new SBR3 tank and installation of SBR3 equipment.
Construction of EQ tank and installation of EQ tank pump.
Construction of thickener platform and chemical room with thickener package equipment installation including thickener, thickener sludge feed pump and polymer system.
Construction of WAS tank.
Installation of a new domestic water lines with emergency eye wash/shower and electric hot water tank in the polymer room.
Installation, programming and commissioning of instrumentation and controls for the above-mentioned equipment.
Testing, commissioning of all equipment and process areas and switch over to District ownership.