Additional Scope Items

  • Demolition and disposal.
  • Siteworks including ground improvements for structural foundations, grading, drainage, fencing, retaining walls, site dewatering and landscaping.
  • Construction of above-ground, glass-fused, bolted-steel reservoir.
  • Mechanical piping, valves, fittings and appurtenances.
  • Upsizing existing valve chamber.
  • Electrical and instrumentation to service the new facilities.
Project DetailS

Building the Future with Expertise & Innovation

This project involved the demolition and disposal of an above ground concrete potable water reservoir (Harvey Tank), including electrical devices, piping and appurtenances, and construction of a new 2.33 ML above-ground glass-fused bolted-steel reservoir to store potable water. The reservoir includes a geodesic aluminum dome roof.

Harvey Creek Reservoir Tank Replacement Project Timelapse

Challenges
  • Retrofitting a decommissioned above ground concrete tank (Oceanview) to use during demo and construction of the new water tank.
  • Work needed to be planned appropriately to ensure low water storage periods did not coincide with high fire risk periods.