Industra 2020 Logo - White Letters - Transparent Background

Employee Portal

Search

Work continues …

Chilliwack Non-Linear Utilities Design-Build

Chilliwack, British Columbia
This multi-discipline project combines several independent water and sewer upgrade and replacement projects into a single design-build project that includes the replacement of a wet well at an existing sanitary pump station, replacement of two water booster pump stations, construction of a new water reservoir, installation of a new water booster pump station and installation of several noise abatement measures at a water production well.
Additional Scope Items
New Booster Pump Stations
  • Design and construct a 15 L/s and a 35 L/s duplex water booster pump station (BPS) utilizing turbine pumps.
  • Existing BPS to remain in operation at all times during construction.
  • Provide flow meter on downstream side of new BPS.
  • Supply and install vertical turbine pumps, each capable of supplying water at 15/35 L/s at 86/7m of pumped total head into the 200/600mm DI main supplying zone.
  • Supply and install all required electrical, mechanical and structural components for BPS.
  • Connect the new BPS to the existing on-site backup generator and control building.
  • Design and construct water main (yard piping) to connect the new BPS to the steel inlet/outlet main.
Production Well Noise Abatement Upgrades
  • Perform detailed design, supply and installation of three types of noise abatement measures, including acoustic louvers, hospital grade combustion mufflers, and sound absorption treatment such as Tectum Finale panels.
New Sanitary Pump Station
  • Design and construct new duplex sanitary pump stations (SPS) with duty/standby pumps and wet well sized to accommodate a peak wet weather flow of 15 L/s to 35 L/s.
  • Supply and install an external weatherproof enclosed diesel generator sized to the stations pumps and loads with a minimum power rating of 20kW and sound rated to a maximum of 67 db at 7m.
  • Connect the existing 200mm PVC gravity sewer and all other service lines to the existing wet well and/or gravity to the new SPS wet well.
  • Design and install a new 150mm forcemain to connect the new SPS to the existing 600mm AC or the 750mm PVC forcemain.
  • Decommission existing SPS and wet well including removal of pumps, piping and appurtenances.

Chilliwack Non-Linear Utilities Design-Build

Chilliwack, British Columbia
This multi-discipline project combines several independent water and sewer upgrade and replacement projects into a single design-build project that includes the replacement of a wet well at an existing sanitary pump station, replacement of two water booster pump stations, construction of a new water reservoir, installation of a new water booster pump station and installation of several noise abatement measures at a water production well.
Additional Scope Items
New Booster Pump Stations
  • Design and construct a 15 L/s and a 35 L/s duplex water booster pump station (BPS) utilizing turbine pumps.
  • Existing BPS to remain in operation at all times during construction.
  • Provide flow meter on downstream side of new BPS.
  • Supply and install vertical turbine pumps, each capable of supplying water at 15/35 L/s at 86/7m of pumped total head into the 200/600mm DI main supplying zone.
  • Supply and install all required electrical, mechanical and structural components for BPS.
  • Connect the new BPS to the existing on-site backup generator and control building.
  • Design and construct water main (yard piping) to connect the new BPS to the steel inlet/outlet main.
Production Well Noise Abatement Upgrades
  • Perform detailed design, supply and installation of three types of noise abatement measures, including acoustic louvers, hospital grade combustion mufflers, and sound absorption treatment such as Tectum Finale panels.
New Sanitary Pump Station
  • Design and construct new duplex sanitary pump stations (SPS) with duty/standby pumps and wet well sized to accommodate a peak wet weather flow of 15 L/s to 35 L/s.
  • Supply and install an external weatherproof enclosed diesel generator sized to the stations pumps and loads with a minimum power rating of 20kW and sound rated to a maximum of 67 db at 7m.
  • Connect the existing 200mm PVC gravity sewer and all other service lines to the existing wet well and/or gravity to the new SPS wet well.
  • Design and install a new 150mm forcemain to connect the new SPS to the existing 600mm AC or the 750mm PVC forcemain.
  • Decommission existing SPS and wet well including removal of pumps, piping and appurtenances.

Work continues …