Additional Scope Items

Owner: FortisBC Energy Inc.

Consulting Engineer: MQN Architects, AES Engineering Ltd., SSDG Interiors Inc.

Project DetailS

Building the Future with Expertise & Innovation

Phased renovation of the existing Tilbury T1A control building completed within an active industrial facility operating 24/7.

The project included reconfiguration of the control room, lunchroom, changerooms, and washrooms, along with the addition of a new upper-level office and meeting area. The work involved structural steel installation for second-floor framing and stairs, architectural upgrades, and full mechanical and electrical system integration.

Execution required detailed phasing, temporary works, and continuous coordination to maintain uninterrupted facility operations while delivering upgrades within occupied and critical-use spaces.