Owner: City of Sault St. Marie
he East End Wastewater Treatment Plant Settlement Mitigation project involves the remediation of long-term settlement affecting critical wastewater treatment infrastructure, specifically the Primary Clarifier and Bioreactor structures. Since the facility’s construction in 2005, settlement exceeding 295 mm has been observed due to compressible clay deposits and loading from surrounding fill materials. The selected remediation strategy consists of underpinning the existing structures with deep H-pile foundations, installing structural support brackets, constructing new inlet and outlet chambers, and placing lightweight fill to reduce future loading and mitigate ongoing settlement risks. The project is being undertaken within an active wastewater treatment facility where continuous plant operations and protection of existing infrastructure are critical.